Time and Work MCQs

A and B together can finish a job in 8 days, B and C in 12 days, and A, B and C together in 6 days. How long will A and C together take?

  • A. 4 days
  • B. 6 days
  • C. 8 days
  • D. 12 days

A alone can do a work in the same time as B and C together. If A and B together take 10 days, and C alone takes 50 days, how many days will B alone take?

  • A. 15 days
  • B. 20 days
  • C. 25 days
  • D. 30 days

A and B can do a job in 15 and 10 days respectively. They start together but B leaves after 2 days. A alone finishes the rest. In how many days in total is the work completed?

  • A. 8 days
  • B. 10 days
  • C. 12 days
  • D. 15 days

A and B together do a job in 72 days, B and C in 120 days, and A and C in 90 days. How long would A alone take?

  • A. 80 days
  • B. 100 days
  • C. 120 days
  • D. 150 days

Twenty women do a job in 16 days; sixteen men do it in 15 days. What is the ratio of one man's work to one woman's?

  • A. 3:4
  • B. 4:3
  • C. 5:3
  • D. Data inadequate

X and Y take 20 and 12 days respectively. X works alone for 4 days then Y joins. How many days in total?

  • A. 6 days
  • B. 10 days
  • C. 15 days
  • D. 20 days

A and B together finish a task in 1.2 days. A alone takes 20 days. If B works only half a day each day, how many days will they take?

  • A. 10 days
  • B. 11 days
  • C. 15 days
  • D. 20 days

A, B and C can do work in 20, 30 and 60 days respectively. If B and C assist A every third day, how many days to finish?

  • A. 12 days
  • B. 15 days
  • C. 16 days
  • D. 18 days

A+B take 6 days, B+C 12 days, A+C 8 days. If all three work together, how many days to finish?

  • A. 4⅔ days
  • B. 4 days
  • C. 5⅓ days
  • D. 1⅓ days

B is three times as fast as A. Together they finish a job in 1 day. How long would B alone take?

  • A. 32 hours
  • B. 48 hours
  • C. 3 days
  • D. 4 days

4 men and 2 women finish work in 2 days. 2 men alone take 5 days. How many days for 2 women alone?

  • A. 15 days
  • B. 10 days
  • C. 8 days
  • D. 20 days

A and B take 9 and 12 days separately. They work alternately one day each, A starting. How long to finish?

  • A. 42/4 days
  • B. 41/4 days
  • C. 55 days
  • D. None of these

Two fill pipes take 10h and 12h; a drain empties in 20h. All three open together, how long to fill?

  • A. 7.5 hrs
  • B. 5 hrs
  • C. 7 hrs
  • D. None of these

Two fill pipes together fill in 6h; one pipe is 5h faster than the other. How long for the slower?

  • A. 5 hrs
  • B. 10 hrs
  • C. 15 hrs
  • D. 20 hrs

A can do work in 6 days, B in 8 days. They finish with C’s help in 3 days. What is C’s share of the total wages of Rs. 3200?

  • A. Rs. 380
  • B. Rs. 600
  • C. Rs. 420
  • D. Rs. 400

A completes in 12 days at 8h/day; B in 8 days at 10h/day. Together at 8h/day, how many days?

  • A. 5 5/11 days
  • B. 4 5/11 days
  • C. 6 4/11 days
  • D. 6 5/11 days

P+Q=30 days, Q+R=24, R+P=20. They all start; Q and R leave after 10 days. How many more days will P need?

  • A. 10
  • B. 8
  • C. 18
  • D. 19

X+Y=10 days, Y+Z=16, X+Z=22. How many days for each alone?

  • A. 120, 40, 60 days
  • B. 120, 60, 80 days
  • C. 40, 30, 120 days
  • D. 30, 40, 60 days

A and B together finish in 20 days, B and C in 30 days, C and A in 40 days. How long for A alone?

  • A. 48
  • B. 34⅖
  • C. 44
  • D. 45

Bilal takes 15 days and Jalal 12 days. After 4 days of working together, what fraction remains?

  • A. 3/5
  • B. 4/7
  • C. 2/5
  • D. 1/4

2 men & 12 women finish in 4 days; 4 men & 6 women in 5 days. Find days for 1 man & 1 woman.

  • A. 30 days
  • B. 25 days
  • C. 24 days
  • D. 20 days

A alone in 10 days, B alone in 15 days. Sharing ₹75 wage, what does A get?

  • A. ₹35
  • B. ₹40
  • C. ₹45
  • D. None of these

P, Q & R pipes fill in 20, 15 & 12 min. together how long?

  • A. 5 min
  • B. 10 min
  • C. 15 min
  • D. 20 min

Two fill taps 12 & 15 min; outlet open too, fill in 20 min. How long to empty full tank?

  • A. 10 min
  • B. 20 min
  • C. 30 min
  • D. 40 min

6 men & 8 women finish in 10 days; 26 men & 48 women in 2 days. How many days for 15 men & 20 women?

  • A. 4 days
  • B. 6 days
  • C. 2 days
  • D. 8 days

P is 30% more efficient than Q. P alone takes 23 days. Together, how many days?

  • A. 9
  • B. 11
  • C. 23
  • D. 13

P works twice as fast as Q. Q alone takes 12 days. Together, how many days?

  • A. 1
  • B. 2
  • C. 3
  • D. 4

6 men do 50 tasks in 4h. How many tasks can 10 men do in 6h?

  • A. 20
  • B. 25
  • C. 125
  • D. 60

A (8d), B (14d), C (16d). A works 2d, B then completes 2/3 of remaining, C finishes rest. How many days?

  • A. 13
  • B. 11
  • C. 12
  • D. 15

A and B in 21 & 24 days start together; after A leaves B needs 9 more days. After how many days did A leave?

  • A. 5
  • B. 6
  • C. 7
  • D. 8

A in 30 days, B in 40 days separately. Together, how many days?

  • A. 70 days
  • B. 120/7 days
  • C. 50 days
  • D. 45 days

A in 12 days; B is 60% more efficient. How many days for B?

  • A. 12/6 days
  • B. 15/2 days
  • C. 23 days
  • D. 34 days

P & Q fill cistern in 12 & 16 min. together, then Q closed. After how many minutes must Q be closed to fill in 9 min?

  • A. 2 min
  • B. 3 min
  • C. 4 min
  • D. 5 min

P, Q & R take 24, 6 & 12 days. Working together, how many days?

  • A. 2
  • B. 3⅗
  • C.
  • D. 5

20 women finish in 16 days; 16 men in 15 days. Ratio of man to woman capacity?

  • A. 1:3
  • B. 4:3
  • C. 2:3
  • D. 2:1

10 bulls plough 20 fields in 3 days of 10h. In how many days will 30 bulls plough 32 fields in 8h days?

  • A. 2
  • B. 8
  • C. 10
  • D. 12

A lays track in 16 days, B in 12 days. With C they finish in 4 days. How long for C alone?

  • A. 4
  • B. 9.6
  • C. 9
  • D. 10

12 men in 20 days; 20 women in 16 days. Ratio man to woman capacity?

  • A. 3:4
  • B. 5:4
  • C. 4:3
  • D. 5:3

A and B do a job in 12 days; B and C in 15; C and A in 20. How long for A alone?

  • A. 20 days
  • B. 30 days
  • C. 40 days
  • D. None of these

A tap fills in 32 min and another empties in 16. If cistern is half-full and both opened, how long to fill?

  • A. 12 min
  • B. 14 min
  • C. 16 min
  • D. 20 min

Leak empties full tank in 6h; inlet fills at 4 L/min. When tank is full inlet opens and empties in 8h. What is capacity?

  • A. 5750 L
  • B. 5760 L
  • C. 6890 L
  • D. None of these

P alone does in same time as Q+R. P+Q in 10 days, R in 50 days. How many days for Q alone?

  • A. 30 days
  • B. 25 days
  • C. 20 days
  • D. 15 days

10 men take 7 days; 10 women take 14 days. How many days for 5 men and 10 women?

  • A. 7
  • B. 5
  • C. 6
  • D. 4